Just a quick update to let you know that we will start testing PowerConvert this week. Tests will probably continue into next week but things are a bit slow due to the holidays at the moment. If all goes well with PowerConvert I will start ordering the first two production environment machines from HP.
We have also made a list of the things we will not be migrating:
- The Faxserver
- The Exchange Servers (not until full 64 bit host support so we can upgrade to Exchange 2007)
- The Cisco Callmanager servers
These are the things we know for sure. If anything changes I will post it here ofcourse.