After 6 weeks of this project we have reached the following status:
- 2 ESX 3.0.1 hosts online and clustered
- 24 VM’s in production of which there are:
- 6 Linux servers
- 18 Windows servers
- Average CPU resource use: 2Ghz of a total available of 38Ghz
Posted by martijnl on November 13, 2006
After 6 weeks of this project we have reached the following status:
Posted in BlogPosts | Tagged: project | Leave a Comment »
Posted by martijnl on November 13, 2006
Three conversions last Thursday and again something to write about.
I would like to report some sort of consistency in the process but it seems everytime there has to be something that needs extra attention.
In this case there were:
Posted in BlogPosts | Tagged: migration, p2v | Leave a Comment »